The challenge posed by falling minimum demand was again in the spotlight this week with the release of the latest supply assessment by the Australian Energy Market Operator (AEMO).
The 2021 Electricity Statement of Opportunities (ESOO) highlights the major impact the increasing amount of distributed PV, particularly solar systems going on household rooftops is having on managing the grid. In its central scenario the market operator expects to see nearly 9GW of PV installed within the next four years, on top of 14GW of capacity already installed.
One outcome of this continuous growth is that each mainland National Electricity Market (NEM) region can expect to see minimum demand occur in the middle of day from now on. This has become increasingly evident since 2018-19 when around 75 per cent of minimum demand events in these regions occurred between midday and 2:30pm.
Individual states have already had to contend with the challenge of increasing periods of minimum demand with South Australia leading the way – that state has achieved periods of up to 78 per cent of underlying demand being met by rooftop solar and the market operator expects that under some scenarios distributed solar could be supplying 100 per cent of underlying demand at times as early as this spring. In other states distributed PV has met up to 42 per cent underlying demand in Victoria, 38 per cent in Queensland, and 32 per cent in New South Wales.
On 10 October last year a record of 35 per cent of underlying demand in the mainland NEM[i] (excluding Tasmania) was met by distributed PV and operational demand hit a new minimum record of 13.6GW. Within five years AEMO expects rooftop solar to supply up to 77 per cent of underlying demand in mainland NEM regions at times.
The extent of the shift expected is underlined by the forecast that minimum demand could be in a range of around 4-6GW by 2025 in all mainland NEM regions (central scenario, see figure 1). The market operator has also flagged that “extreme actions” might be required in some circumstances if operational demand fell below that threshold and there is not action to address the operational challenges. AEMO estimates that 4-6GW is the minimal operational demand required with its present operational toolkit.
Figure 1: Minimum demand in NEM mainland
Source: AEMO, 2021 ESOO
Across the Bass Strait, while Tasmania has had several midday minimums these have tended to be driven by reductions in large industrial loads. But in future AEMO expects to start to see minimum demand occur in middle of the day in the Apple Isle as well.
An early challenge
In the short-term, mainland NEM jurisdictions are expected to see minimum demand fall rapidly with the expectation of more distributed PV compared to the 2020 ESOO, and this is expected to accelerate the need for complementary market-based and operational support earlier than previously forecast.
This decline will become more subdued the closer we get to 2030-31 (the end of the 10-year projections in the ESOO) with the forecast growth in electric vehicles and battery storage shifting some of the demand dynamics.
But in the meantime it is posing increasing challenges to the operation of the grid. There are thresholds for demand beyond which the stability of the grid is challenged, and the market operator expects those threshold levels to be reached within five years in the whole mainland NEM. Even when Snowy 2.0 starts operating, the additional load resulting from its pumped storage is still not considered enough on its own to address long-term system security challenges.
The fundamental issue, as outlined in the ESOO, is that minimum operational demand driven by rooftop solar largely represents uncontrolled demand. AEMO has flagged a number of areas where the increased volume of rooftop solar gives rise to challenges and where adaptations are needed:
Extreme action
While there is an expectation that NEM mainland operational demand could reach the 4-6GW range by 2025 (if not earlier under some scenarios) there is a concern that increasingly challenging periods could occur in some periods before those levels are reached. This would arise if there were abnormal circumstances, such as network and/or plant unit outages, or as a result of extreme events like bushfires and storms. At the same time, some of these challenging periods could occur earlier for individual regions in circumstances where they are islanded.
The ESOO warns that if operational demand falls below the 4-6GW range “it will become increasingly necessary to take extreme actions”. Those could include selectively disconnecting whole distribution feeders where they are feeding electricity back into the grid. Disconnecting feeders would increase the operational load, but it “also means that all consumers on the feeder lose power supply”. This would be done to avoid the potential for a black system.
Based on the current operational capabilities in the system consumers on feeders with high levels of rooftop solar could be without power “potentially for extended periods during daylight hours” and “potentially on repeated days during shoulder seasons” - spring and autumn which is when minimum demand often occurs due to milder weather accompanied by plenty of sunshine.
If shedding consumer feeders is not sufficient to recover enough load in some regions there would be the risk of a contingency event, such as generator trip or network fault leading to a “cascading failure to a black system”.
The operator is concerned that if there aren’t adaptations to the system “it is foreseeable that there could be extended periods for many hours during the middle of the day and over repeated consecutive days where the NEM or parts of the NEM may not be secure”.
Adaptations
The market operator points to adaptations under the categories of:
[i] Mainland NEM regions are NSW (including the ACT), Victoria, Queensland and South Australia. The full NEM includes Tasmania in addition to these regions.
There has been growing concern about inflationary pressures, the prospect of higher interest rates and higher fuel costs for the economy generally. But what do these factors mean for electricity prices? We have taken a detailed look at the factors at play and how they are likely to determine and influence our power prices.
North Queensland attracts its fair share of debate around electricity. Since around 2009 there has been a push to develop a major transmission line – now CopperString 2.0 (CopperString) – to connect Mt Isa to the National Electricity Market. Discussion around the CopperString proposal has come back into focus recently with submissions to the Queensland Government on electricity supply options for the North-West Minerals Province. Here we take a closer look at the CopperString proposal, the project’s background, options moving forward and the costs and benefits.
The transition of the energy grid continues apace and its impacts on how the system operates continue to evolve. The latest GenInsights21 report provides valuable insights into some of the key trends that are emerging, this is based on analysis of extensive generation data. We take a look at its assessment of the expansion of rooftop solar and the implications for the grid.
Send an email with your question or comment, and include your name and a short message and we'll get back to you shortly.