May 26 2016

Turning it to the right frequency on renewables

In late 2015, during a planned outage of part of the Heywood interconnector between Victoria and South Australia, the Australian Energy Market Operator (AEMO) purchased additional Frequency Control Ancillary Services (FCAS) in South Australia. AEMO’s decision was based on the need to keep the power system stable in the event that the remaining interconnector tripped and this resulted in very high FCAS costs.

AEMO procures FCAS to ensure that the power system remains secure if there are unexpected events, such as the loss of a generator or an interconnector. The efficient procurement of FCAS will be an essential part of the process of managing the integration of highly variable renewables to the National Electricity Market (NEM) because they assist AEMO to balance the grid and mitigate the risk of outages.

It is the intermittent nature of new renewable electricity that creates challenges for systems and markets that were designed around dispatchable generators such as hydro, nuclear or fossil-fuelled plants. These conventional plant types also have characteristics that allow them to contribute to the stability of the grid, including keeping frequency and voltage levels consistent and being able to restart the system after a major blackout. Solar is not designed to contribute in this way, and while wind can (in limited cases) assist, its intermittency precludes its use as a reliable source for grid stability[i].

At current levels, the intermittency (particularly from wind) is having a material impact on South Australia’s electricity market, as well as the security of the electricity grid. The challenge of integrating renewables is likely to require AEMO to procure more stabilising services such as FCAS to ensure a secure power supply and avoid blackouts, at the same time as the supply of FCAS will decrease.

Figure 1: High FCAS price in SA during October and November 2015, moving avg.

Source: Moving average 7 day, derived by the Australian Energy Council from AEMO, 2016

The increase in renewable generation, like wind and solar PV, which are highly variable will in turn reduce the amount of dispatchable generation that provides FCAS[ii]. As potential suppliers of FCAS decrease, it is likely that the price of FCAS will increase, if all else is held constant.

AEMO estimated that normally costs for the total quantity of FCAS required in the NEM between October and November 2015 would have been around $500,000. The actual cost during the Heywood outage was approximately $27 million[iii]. The majority of these costs will eventually be charged to consumers after being recovered from market participants in South Australia[iv].

On 9 May 2016, Alinta’s Northern and Playford power stations were closed (Playford had previously been mothballed), removing stabilising synchronous generation from the South Australian region. In the period of time since the closure, South Australia has been reliant on wind for 60 per cent of generation[v]. The impact of this change in supply and higher penetration of renewables is seen in the prices for FCAS on the day of the closure, and shortly after, as AEMO and the market adapted to the exit.

Figure 2: SA FCAS price during May 2016, around the Alinta plant closures

Source: AEMO, 2016

AEMO has relied heavily on power system-stabilising services provided by fossil fuel generators which have been relatively abundant and low cost[vi]. As renewables become a larger share of the energy mix the supply of power system-stabilising services will fall. At the same time, higher amounts of renewable energy will increase the need to stabilise the power system and increase demand for FCAS. AEMO’s current measures to address stability are sufficient. But as the power system continues to evolve, there will be a need for changes to market arrangements or infrastructure to continue to meet security and reliability expectations.



[ii] NREL, 2014, http://www.nrel.gov/electricity/transmission/electricity_market.html

[iii] AEMO, 2016, NEM – market event report – high FCAS prices in South Australia, Melbourne, page 11

[iv] AEMO, 2016, NEM – market event report – high FCAS prices in South Australia, Melbourne

[v] AEMO, 2016, generation data from 10 to 17 May 2016, compared to 50 per cent at the same time in 2015.

[vi] AEMO ElectraNet, 2016, Renewable energy integration in South Australia, http://www.aemo.com.au/Electricity/Market-Operations/Power-system-security

Related Analysis

Analysis

The best little blackout in Texas

They say everything’s bigger in Texas. The major power outages from which it is just emerging, were triggered by a polar vortex and impacted around 4.5 million customers. There's been plenty of finger pointing with intermittent renewables being blamed, questions raised about Texas’s go-it-alone attitude and claims of poor preparations stemming from a deregulated energy market.

Feb 25 2021
Analysis

Dropping demand and plunging prices: Can you have too much of a good thing?

The fourth quarter of 2020 saw the NEM reach lowest average demand since Q4 2001 – with SA and Victoria’s spot prices hitting record lows. Are customers benefiting from the price suppression effects of renewable energy generation? Or is the market telling us a different story?

Feb 18 2021
Analysis

Big battery bonanza?

The way 2021 has started, you could be forgiven for thinking it is the year of the big battery. Plans for the “world’s largest battery” were unveiled for the Hunter Valley, while Meridian Energy announced a battery energy storage system to be co-located with the Hume Hydro Power Station. These are just the latest in a series of big battery project announcements.

Feb 11 2021
GET IN TOUCH
Do you have a question or comment for AEC?

Send an email with your question or comment, and include your name and a short message and we'll get back to you shortly.

Call Us
+61 (3) 9205 3100