Jan 21 2016

Tasmania: When it doesn't rain, it pours

A coincidence of events in Tasmania, with low rainfall causing low dam water storage levels resulting in decreased electricity generation from hydroelectricity and a fault in the Basslink interconnector, has led to wholesale prices surpassing $100 per megawatt hour ($/MWh) for the first time in over five years. The circumstances have also raised questions about the security of supply in the state. Below we take a look at the factors involved and the measures underway in response to the reduced supply.

Water levels

Tasmania experienced the eighth-driest year on record in 2015, partly due to the strong El Niño, according to the Bureau of Meteorology (BOM). The Tasmanian Energy Minister, Matthew Groom, has confirmed that water storage levels are projected to reach a low of about 14 per cent, assuming long-term average rainfall, towards the end of March or in early April 2016[i]. Dam storage levels are currently at 20 per cent.

Hydroelectricity accounts for 74 per cent of Tasmania’s generation capacity, generating 87 per cent of Tasmania's electricity in 2013-14, according to the Electricity Gas Australia publication statistics[ii]. Based on the BOM’s annual summary the second half of 2013 was very wet, in contrast to 2015, when generation from hydro decreased due to the low rainfall as shown in Figure 1 below.

Figure 1: Tasmanian Hydro Generation – 2009-2015 [iii]

The introduction of the Federal Government’s carbon tax and high dam levels contributed to a significant increase in hydro output in 2012 and 2013. The abolition of carbon pricing on 1 July 2014 removed the additional incentive for low emissions generation that the market had seen since 1 July 2012 and has reduced the profitability of future hydro generation. Combined with that, the recent below average rainfalls have resulted in the lowest level of hydro generation since the 2008-09 droughts.  

Basslink fault

The Basslink interconnector fault in the undersea power cable experienced on 20 December 2015 was detected about 100 kilometres off the Tasmanian coast and at a depth of about 80 metres. At the time of writing the cause of the fault was still being investigated. The importance of the interconnector is underlined by the fact that during late 2015, Tasmania had been importing about 40 per cent of the state's electricity needs from Victoria because of the low water storage levels in the state[iv].

Restoration of Basslink is expected to take up to nine weeks to complete, which would see it fully operational by the 19 March 2016[v].

Prices reach record highs in Tasmania

Last month Tasmania’s weekly volume weighted spot prices (VWP) surpassed $100/MWh. It was the first time the weekly VWP passed $100/MWh in Tasmania since 8 August 2010 when the weekly price reached $154/MWh. Figure 2 and 3 show the weekly VWP movements since 2010.

Figure 2: Weekly volume weighted average spot prices 2010-2015 – Tasmania[vi]

Figure 3: Weekly volume weighted average spot prices 2015 – Tasmania[vii]

It is important to note that under the Tasmanian wholesale contract regulatory framework, the Tasmanian Economic Regulator regulates electricity contracts that Hydro Tasmania has been required to offer for sale to other electricity market participants since 1 January 2014.

From 20 September 2015 to the end of December last year the weekly VWP has increased consistently. The higher than average prices have occurred because of scarce supply as a result of the low rainfall and interconnector issues.

Where to next?

After the driest September to November period on record in 2015, Hydro Tasmania announced the restart of the combined cycle gas turbine at the Tamar Valley Power Station. The CCGT was recommissioned on 20 January 2016. The unit had not generated power for more than 18 months[viii] and had been earmarked for sale. Hydro Tasmania had not used the CCGT while there was ample hydro generation and imports from Victoria were cheaper.[ix]

The CCGT remains a commercially sensible addition in the short-term to the Tasmanian energy supply mix. The sale of the unit is currently off the table with the State Government withdrawing its previous approval following the failure of Basslink. The future of the unit will now be reviewed[x].

Despite the current situation, the State Government and Hydro Tasmania have indicated that under normal operating circumstances, there is enough energy to meet Tasmanian demand through the combination of future hydropower inflows, wind generation and the import capacity of Basslink, which is expected to come back to full capacity by late March 2016.

Tasmania has diversified its energy mix with the inclusion of wind in addition to gas and hydro energy. Currently there is 308 MW of large-scale wind connected. This could increase in coming years with over 700 MW of proposed wind capacity[xi] from a range of private developers.

 


[i] Tasmanian Premier Will Hodgman, Media Release 14 January, http://www.premier.tas.gov.au/releases/basslink2

[ii] ESAA, Electricity Gas Australia 2015

[iii] Source: NEM Review , Data: Metered Generation

[iv] ABC News article, 2015, Hydro Tasmania to fire up Tamar Valley Power Station in 2016, http://www.abc.net.au/news/2015-12-16/hydro-tasmania-to-fire-up-tamar-valley-power-station-in-2016/7034550

[v] Basslink, 2015, Basslink interconnector update, http://www.hydro.com.au/system/files/documents/Basslink/Basslink_Media_statement_140116.docx_.pdf

[vi] Source: NEM Review/ Australian Energy Regulator (AER)

[vii] Source: NEM Review/ Australian Energy Regulator (AER)

[viii] Hydro Tasmania media, 2015, Hydro Tasmania to restart combined cycle gas turbine, http://www.hydro.com.au/about-us/news/2015-12/hydro-tasmania-restart-combined-cycle-gas-turbine

[ix] Hydro Tasmania media, 2015, Changes to operation of Tamar Valley Power Station, http://www.hydro.com.au/about-us/news/2015-08/changes-operation-tamar-valley-power-station

[x] Tasmanian Government, 2016, Response to the Tasmanian Small Business Council, http://www.premier.tas.gov.au/releases/response_to_the_tasmanian_small_business_council

[xi] ESAA, Electricity Gas Australia, 2015

Related Analysis

Analysis

Queensland’s pumped hydro plans

In September 2022, then Queensland Premier Annastacia Palaszczuk announced plans to construct two new pumped hydro projects: Borumba Dam – a 2GW facility located in Imbil, 50km west of Noosa, and the Pioneer/Burdekin facility which plans to offer 5GW of storage, located 75km west of McKay. We take a look at pumped hydro and how it can support the energy transition.

Apr 11 2024
Analysis

Gas outlook highlights peaking plant role in transition

Apart from raising some alarm bells over future potential gas shortfalls, the release of the Australian Energy Market Operator’s assessment of gas needs again highlighted the important role gas generation will play in the energy transition.  Gas generation is seen increasingly as a “strategic reserve for power system reliability and security” and “will be critical when it runs”. We take a look. 

Apr 04 2024
Analysis

Reviewing the Reviews, Part II

The first meeting of the Energy and Climate Change Ministerial Council (ECMC) for 2024 brought to the fore the extent of change underway in the energy sector. The ECMC’s communique hints at the breadth of reviews and assessments into the energy sector and operations of the National Electricity Market (NEM). It's part of a now long-established pattern. For well over a decade, energy has been at the forefront of policy developments, largely because of the significant changes to our grid. Along with those changes has come a heightened political involvement. With political interest has come a myriad of reviews, assessments and interventions to make the NEM “fit for purpose”. We take a look at the latest ECMC work and the extent of reviews underway.

Mar 07 2024
GET IN TOUCH
Do you have a question or comment for AEC?

Send an email with your question or comment, and include your name and a short message and we'll get back to you shortly.

Call Us
+61 (3) 9205 3100