Jun 01 2017

2018: The summer of demand response

The closure of Hazelwood Power station in March and Northern Power station in May last year has significantly reduced reserve margins for electricity in those two states.  This is most acute during the summer months, when demand in these regions is traditionally at its peak for the year.

The Australian Energy Market Operator (AEMO) has identified low reserve conditions for both South Australia and Victoria this summer, which is a probabilistic assessment that there is the risk of insufficient generation reserve required to comply with the prescribed reliability standards. Or in other words there is an increased risk of supply shortage resulting in blackouts.

Concerns over supply shortages leading to blackouts has triggered a reaction by governments and business.  Even if the commercial conditions were favourable, it is not possible to build new power stations in six months.

The South Australian government is trying to get 100 MW of storage installed before the start of summer.  The Victorian Government is similarly looking to develop 20 MW of storage, with the option of another 80 MW.  The South Australian Government is also installing 200 MW of temporary diesel generation for the summer.

In March, Engie contracted gas supply with Origin to bring the second unit at Pelican Point power station in Adelaide back on line, whilst, AEMO has been working with generators and transmission businesses to ensure that all existing generation and transmission capacity is available and ready this summer.

Here comes the RERT

These measures have focused on augmenting supply during times of peak demand.  AEMO is also working on measures to enlist a response by industrial energy consumers.  The Reliability and Emergency Reserve Trader (RERT) is a mechanism under the National Electricity Rules that enables AEMO to contract for additional electricity reserves where it anticipates there will be a shortfall.

The RERT has been called three times in the history of the NEM but never activated.  It has had low engagement over the past decade mainly as a result of a surplus of generation.  Not anymore.  AEMO is currently looking to contract around 600 MW of demand side opportunities in Victoria from early January to the start of March 2018[i] (see figure 1), and up to 80 MW in South Australia over the same period[ii] (see figure 2).

Figure 1: Victoria demand side opportunities under RERT 2018

Source: AEMO, 2017
Figure 2: South Australia demand side opportunities under RERT 2018

Source: AEMO, 2017

Recent changes to the RERT mechanism will remove long term contracting and enable AEMO to contract more flexibly, to enable a wider group of suppliers of reserve to participate.  AEMO will now be able to pay businesses for contracting RERT capacity as well as payments in the event the contract is invoked.  This will enable businesses which need investment to be able to supply capacity.

Suppliers of reserve can provide either generation or demand response of more than 10 MW, providing it is firm and that supply or demand response is not already contracted.  Reserve can be aggregated to reach the 10 MW threshold.

Each RERT contract is likely to be bespoke depending on the lead time needed by the facility or aggregator to supply firm reserve in the event it is called on.  Some large energy customers like smelters may be able to reduce demand in a few minutes, while others may need 24 hours or more to cancel shifts and switch off production.

AEMO is calling for expressions of interest until early July, and will then call for tenders to contract reserve after that.  The size of the RERT market will continue to evolve as AEMO updates its medium term forecasts for next summer.  Given the electricity demand-supply balance is now increasingly weather dependent (high temperatures increase demand and wind increases supply), it will only be inside the actual weather forecasting window of a week or so when RERT contracts will be activated.

It may be a steep learning curve for AEMO to find and manage 600 MW of reserve after a decade where the mechanism was largely dormant.  In theory there may be a number of businesses that would be willing to contract off their electricity during extreme heat waves.  But AEMO has to find them and then schedule them over a 48 day window with some sort of efficiency.

It’s also worth noting that the revised RERT opens up the provision of capacity payments for demand response, even though it remains an energy-only market for generation.  It does suggest the value of capacity, particularly under peak demand conditions, is increasing as we evolve to an electricity system with higher intermittent generation. The continuing creep of payments to selected resource types, whatever the rationale, further weakens the ability of the energy-only market to deliver revenue adequacy to market participants.

AEMO-ARENA demand response pilot

Earlier this month AEMO also announced a 100 MW three year demand response pilot for South Australia and Victoria in conjunction with the Australian Renewable Energy Agency (ARENA).

The program will also provide capacity payments for energy users who make their energy available for periods of extreme demand and will be open to both commercial and residential consumers as well as aggregators.

What is apparent from this escalated activity in demand response is that it is likely to be a significant feature of electricity markets into the future.  Constraints on new generation investment and increased supply from intermittent generation means demand has to become more flexible to match variable supply.

While demand response is basically switching off supply (or its equivalent using storage and other technologies), it can serve multiple purposes.  Targeted local DR can be used to avoid network augmentations.  More broadly DR can be used to avoid investment in peaking generation and reduce the cost impact of demand peaks.  And finally DR can be contracted for “emergency” events as is being targeted by the RERT.

As with other aspects of energy supply, consumers do not know or want to know the complexities of these operational arrangements.  They will sign on to DR deals when they think the deal being offered is worth it.  This in turn will place greater emphasis on their evolving relationship between consumers and their energy retailer or other competitive energy service provider, to guide this evolving relationship between system and customer as the 21st century grid unfolds.

 


[i] AEMO, Operating Strategy FY2017-18, 2017

[ii] ibid

Related Analysis

Analysis

Energy Dynamics Report - A Tale of Minimum Operational Demand and Wholesale Price declines

The third quarter saw significant price declines compared with the corresponding quarter in 2022 right across the NEM. At the same time with increased output from solar and wind generation inin Queensland’s case, minimum operational demand records were set or equaled in every region. The quarter also saw the highest-ever level of negative price intervals with all regions showing an increase. We dive in to the pricing and operational demand detail of AEMO’s Q3 Quarterly Energy Dynamics Report.

Nov 09 2023
Analysis

Data centres: A 24hr power source?

Data centres play a critical role in enabling the storage and processing of vast amounts of online data. However they are also known for their significant energy consumption, which has raised concerns about their environmental impact and operating costs. But can data centres be fully sustainable, or even a source of power?

Oct 12 2023
Analysis

Demanding a response?

Concerns about the unfulfilled potential of demand response markets in the National Electricity Market has triggered periodic interest in this subject over the past three decades. Is Australia is really lagging behind on demand-side action? We take a look at the options for policy tweaks strengthening the role of demand-side considerations in energy system planning.

Feb 02 2023
GET IN TOUCH
Do you have a question or comment for AEC?

Send an email with your question or comment, and include your name and a short message and we'll get back to you shortly.

Call Us
+61 (3) 9205 3100